How long does it take to build a corporate website?

It depends on scope. A corporate website of around twenty pages typically takes six weeks to two months from defining the structure to launch. Numerous product models, two or three languages at once, or content waiting on the client will extend the timeline. The single biggest factor is always who provides the content; the detailed schedule is written into the scope list.

A corporate website of around twenty pages typically takes six weeks to two months from defining the structure to launch. Within that period, most of the time goes to confirming the structure and preparing content; coding is only one part.

How the timeline breaks down

  • Structure confirmation, about one week: Define sections, hierarchy, URL rules, and the page inventory. This step may seem slow, but it determines where every subsequent page belongs.
  • Design, one to two weeks: Produce the homepage and one interior page first, then roll out once the visual direction is confirmed. Rolling out all pages before the direction is set is the most costly kind of rework.
  • Development and CMS, two to three weeks: Templates, sections, content models, and forms. Add time if there's a product system and filtering.
  • Content population and integration, one to two weeks: Organize product information, case studies, and images into pages; this step often stalls while waiting for materials.
  • Launch, two to three days: DNS setup, ICP filing (if required), sitemap submission, and structured data validation.

Three common causes of delay

Numerous product models, two or three languages at once, and content waiting on the client. The first two are determined by workload itself and can be factored in ahead of time; the third is a scheduling issue and the most likely to drag—facts like product specifications, certifications, and lead times can only come from you; we won't make them up for you.

Can it be faster?

What can be compressed is the overlap between design and development; what can't is structure confirmation. Starting work before the structure is set usually costs twice the saved week back before launch: changing sections means changing navigation, changing URLs means redirects, and changing hierarchy means rearranging internal links. If you have a fixed launch date (a trade show, a bid, an ad campaign), tell us the date first and we'll define scope by working backward—cutting pages is safer than rushing the schedule.

← Back to FAQ

Tell us about your project

No complete brief is needed. Tell us your target audience, the inquiries you expect, and your current challenges, and we'll give you a structural assessment.

Submit an inquiry

  • No full requirements document needed
  • Same-day reply on business days
  • If it's not a fit, we'll say so — no hard sell

You can also look into Project Workflow, or check outServices & Solutions。